Steris, Daventry

January 11, 2024 | Case Studies

Steris, a global leader in sterilisation and contamination control, has over 40 years of experience in providing safe and effective gamma irradiation sterilisation. Their facility in Daventry experienced an issue with high evaporation in the cobalt pool beneath their gamma room, which was affecting their operations and making it difficult for engineers to work in the hot and enclosed space. Our company was contracted to address this issue and lower the temperature of the room by forcing chilled air into the pool space, ultimately reducing evaporation.

With a tight deadline of a single day of shutdown allowed by Steris, our company faced the challenge of quickly and effectively manufacturing and installing new ductwork systems to replace the existing ones. This had to be done in a way that not only resolved the temperature and evaporation issues but also ensured the long-term safety and effectiveness of the new ductwork.

Our team promptly removed the existing ductwork systems that came up through the floor and replaced them with new 304 grade stainless steel ductwork. Stainless steel was chosen for its excellent resistance to gamma radiation, which can cause damage to materials over time. Additionally, this material is known for its durability and ease of cleaning, making it ideal for use in a sterile environment.

The project was completed successfully within the given timeframe, and the new ductwork systems have significantly lowered the temperature of the room, improving the working conditions for engineers. The use of 304 grade stainless steel in the ductwork ensured that the systems would remain safe and effective for the long term, meeting Steris’ high standards for safety and efficiency.

This case study demonstrates our company’s commitment to providing innovative and efficient solutions for complex challenges, even within tight deadlines. Our expertise in selecting the appropriate materials and executing seamless installations has not only improved working conditions at Steris Daventry but also reinforced the facility’s long-term safety and effectiveness. Our work showcases the dedication and skill that we bring to every project for our clients in the industry.

Steris

Further Reading

January 31, 2024 | Latest News

Introducing Our Comprehensive Ducting Solutions...

Read Post
January 31, 2024 | Case Studies

Frameless, Marble Arch

Read Post
Ducting Direct Collaborates with D&A Sheet Metal Ltd
January 31, 2024 | Latest News

Ducting Direct Collaborates with D&A Sheet ...

Read Post
Stay up to date with everything ducting

    X